Cordiant Digital Infrastructure H1 Earnings Call Highlights

Cordiant Digital Infrastructure (LON:CORD), which is transitioning to the Corilis name, reported portfolio revenue growth of 18.1% and EBITDA growth of 3.5% for the six months ended September 2026, as its acquisition of BT Ireland boosted sales while currency movements weighed on returns.

Executive Chairman Steven Marshall described the period as challenging, citing foreign exchange headwinds and higher government bond yields, which increased the discount rates used in valuations. Net asset value per share rose to £1.458 from £1.437 on an ex-dividend basis six months earlier.

The portfolio’s total NAV return was 4.3% in local currency terms but fell to 1.4% after foreign exchange headwinds of more than £30 million, Marshall said. The company declared an interim dividend of 2.225 pence per share, unchanged from the comparable payment last year.

Acquisition lifts revenue as currency weighs on NAV

Chief Financial Officer Andrew Ewe said EBITDA grew more slowly than revenue partly because Speed Fibre Group’s acquisition of BT Ireland added a lower-margin business. Emitel, the portfolio’s largest company, increased EBITDA by 4%.

Ewe said inflation-linked contract pricing, new multiyear agreements, project revenue and cost discipline supported performance. Hudson’s EBITDA declined during the period, but he said newly signed contracts should bring the business to EBITDA break-even on a run-rate basis in the next financial year. The company was also managing anticipated customer churn.

Every portfolio company increased in value in local currency terms, Ewe said, with Emitel a key contributor. Those gains were offset by a weighted average 25-basis-point increase in the discount rate and sterling’s appreciation against the Polish zloty. Euro exposure is hedged by euro-denominated debt, he added.

The portfolio generated more than £34 million in cash distributions during the period, including a £5 million share capital repayment from CRA. Ewe said the interim dividend was covered 1.8 times by adjusted funds from operations before scheduled debt repayments.

Data center demand supports investment pipeline

Marshall said demand for data center capacity was increasing across the company’s European and U.S. assets. He cited artificial intelligence and customers’ desire to keep sensitive data within national borders as potential drivers, while noting that AI-related activity remained at an early stage.

At the Prague Gateway project, the company has signed letters of intent representing 45 megawatts of potential demand, Marshall said. Those commitments still need to be converted into contracts. Skanska has been awarded a first-phase contract with a capped construction cost of £75 million for the shell, core and initial 4-megawatt data hall.

Marshall said the project could generate at least €25 million in EBITDA once fully sold out, based on the company’s assumptions. He also said the facility could benefit from an EU AI Gigafactory initiative, but cautioned that there were no guarantees and that the process remained at an early stage.

In Belgium, Datacenter United pre-let 3 megawatts of upgraded capacity to Amsterdam-based cloud provider Nebul. Ewe said the €11 million investment in high-density upgrades at the Machelen facility was expected to generate an internal rate of return above 20%.

CRA’s GPU-as-a-service business had £7.1 million in contracted annualized revenue at the end of September, Ewe said. The company has identified up to £100 million of costed investment opportunities in the business and is targeting returns above 20%, with payback periods of less than two and a quarter years.

Funding and management transition

The company has identified more than £400 million of costed organic growth opportunities, about a third of which has been committed, Ewe said. Existing cash, debt and free cash flow are funding committed projects, while management is evaluating options to finance further expansion.

Net debt was approximately 40% of gross asset value, below the company’s 50% limit, and stood at 4.5 times EBITDA. Around three-quarters of drawn debt was fixed or hedged, Ewe said, with no maturities until June 2029. Total liquidity was £186 million, including cash and undrawn facilities.

Marshall also said he acquired Cordiant Capital’s stake in the digital infrastructure manager at the end of September. Following shareholder support for the new name, the business is transitioning to Corilis and expects to move to an externally authorized alternative investment fund manager over the next three months. It will retain the CORD ticker, he said.

About Cordiant Digital Infrastructure (LON:CORD)

Cordiant Digital Infrastructure Limited primarily invests in the core infrastructure of the digital economy – data centres, fibre-optic networks and telecommunication and broadcast towers – in Europe and North America. Further details about the Company can be found on its website at www.cordiantdigitaltrust.com. The Company is a sector-focused specialist owner and operator of Digital Infrastructure, listed on the London Stock Exchange under the ticker CORD. In total, the Company has successfully raised £795 million in equity, along with a debt package that includes a €200m Eurobond with a consortium of blue-chip institutions; deploying the proceeds into six acquisitions: CRA, Hudson, Emitel, Speed Fibre, Belgian Tower Company, and DCU which together offer stable, often index-linked income, and the opportunity for growth, in line with the Company’s Buy, Build & Grow model.